Project overview / 163/2024
Completed

Water project materials & equipment — Salah Al-Din

Supply of operational materials and equipment for water projects and complexes across Salah Al-Din. The contract combined pipeline materials, electrical power equipment and pumping assemblies to support water infrastructure.

Water project materials & equipment — Salah Al-Din
Original project photographs • selected composite
Contract163/2024
ClientSalah Al-Din Governorate / Water Directorate
LocationSalah Al-Din, Iraq
Contract date21 August 2024
Contract statusCompleted

Technical supply specifications

MaterialSpecifications & quantities
HDPE 100 pipes110, 160, 225, 250 and 315 mm diameters; 10 bar operating pressure. Supply schedule quantities: 50,000, 32,000, 18,000, 16,000 and 7,000 m respectively.
Distribution transformers25 × 400 kVA and 12 × 630 kVA; 11/0.416 kV ratio
Submersible pumps55 units; 230 m³/h flow and 25 m head
Horizontal split-case pumps4 complete assemblies; 1,000 m³/h flow, 75 m head and 355 kW motor

Specifications from the project supply schedule; they do not imply company certification.

Documented milestones

21 Aug 2024Supply contract signed
3 Dec 2024Completion date in company correspondence
5 Dec 2024Initial acceptance record
22 Jun 2025Final acceptance record

Scope of work

  • HDPE (high-density polyethylene) pipes
  • Electrical distribution transformers
  • Vertical submersible river-water pumps
  • Complete horizontal pump assemblies

Project documentation

The project records include the supply agreement, administrative orders, inspection and initial acceptance records, and a final acceptance record dated 22 June 2025. Company correspondence records completion on 3 December 2024.