Water project materials & equipment — Salah Al-Din
Supply of operational materials and equipment for water projects and complexes across Salah Al-Din. The contract combined pipeline materials, electrical power equipment and pumping assemblies to support water infrastructure.
Original project photographs • selected composite
Contract163/2024
ClientSalah Al-Din Governorate / Water Directorate
LocationSalah Al-Din, Iraq
Contract date21 August 2024
Contract statusCompleted
Technical supply specifications
Material
Specifications & quantities
HDPE 100 pipes
110, 160, 225, 250 and 315 mm diameters; 10 bar operating pressure. Supply schedule quantities: 50,000, 32,000, 18,000, 16,000 and 7,000 m respectively.
Distribution transformers
25 × 400 kVA and 12 × 630 kVA; 11/0.416 kV ratio
Submersible pumps
55 units; 230 m³/h flow and 25 m head
Horizontal split-case pumps
4 complete assemblies; 1,000 m³/h flow, 75 m head and 355 kW motor
Specifications from the project supply schedule; they do not imply company certification.
Documented milestones
21 Aug 2024Supply contract signed
3 Dec 2024Completion date in company correspondence
5 Dec 2024Initial acceptance record
22 Jun 2025Final acceptance record
Scope of work
HDPE (high-density polyethylene) pipes
Electrical distribution transformers
Vertical submersible river-water pumps
Complete horizontal pump assemblies
Project documentation
The project records include the supply agreement, administrative orders, inspection and initial acceptance records, and a final acceptance record dated 22 June 2025. Company correspondence records completion on 3 December 2024.
Project photo gallery 8 photos
Original photographs documenting the materials and work described in this project.
Original photographs from project records
Inside the project
HDPE pipes at the supply yardPipeline materialsElectrical transformersTransformer unloading and deliveryTransport of packaged equipmentTransformers in the storage yardEquipment inspection before deliveryTransformers loaded for transport