Project overview / 494–497/2024
CompletedElectrical materials — four supply contracts
Four complementary supply contracts for electrical distribution materials: copper cable, aluminium conductor and cable terminals. Each contract covered a defined technical specification and delivery to the client’s warehouses.
PROJECT PROFILE494–497/2024
Electrical materials — four supply contracts
Completed
Contract494–497/2024
ClientMinistry of Electricity / General Company of Middle Electricity Distribution
LocationIraq
Contract date11–12 December 2024
Contract statusCompleted
Scope of work
- 494: 40,000 m of 2 × 2.5 mm² copper cable
- 495: 66,000 m of 70 mm² aluminium conductor
- 496: 4,500 m of 1 × 95 mm² copper cable
- 497: 33,000 pieces of 95 mm² terminals
Project documentation
Contracts, warehouse documentation and inspection records are included in the portfolio. Company letters dated 13 January 2025 record 100% completion for the four contracts.